logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2018.08.08 2017가단27910
건물인도
Text

1. The defendant shall be the plaintiff.

(a) Orderly connect each point of the building indicated in the attached Form 1, 2, 3, 4, and 1, among the buildings indicated in the attached Form.

Reasons

1. Facts of recognition;

A. On March 19, 2013, the part of the building in this case, which connects each point of (A) section 1, 2, 3, 4, and 1 of the attached drawing among the buildings listed in the attached Form to the Defendant in sequence, is 104.4m2

b. The attached building leased the following: (a) monthly rent of 200,000 won from March 19, 2013 to August 19, 2013; (b) the nature and contents of the instant contract were different during the instant lawsuit proceedings; (c) on July 18, 2018, the Defendant kept its machinery and equipment on the instant building on the third day for pleading. (b) The Defendant, as the rent of the instant lease agreement, was KRW 1 million from March 20, 2013; and (d) the period from March 19, 2013 to August 19, 2013 (hereinafter the instant lease agreement was concluded, but the period from January 16, 2014 to June 14, 2014, did not appear to have been extended.

(38 months) Total amount of 7.6 million won is the difference in arrears until August 19, 2017 (38 months’ portion). [Evidence: the absence of dispute, Gap 1 through 7 evidence, and the whole purport of the pleading

2. The plaintiff sought the return, etc. of the above building portion due to the lawsuit of this case. The above lease contract was terminated through the service of the copy of the complaint of this case.

The plaintiff's termination of the contract is justified, since the term of the lease of this case was over and the defendant was in arrears for a long time.

I would like to say.

Therefore, the defendant is obligated to deliver the building portion of this case to the plaintiff, and to pay 7.6 million won in arrears from June 19, 2014 to August 19, 2017 and 200,000 won in monthly rent from August 20, 2017 to the completion date of delivery of the above building portion as requested by the plaintiff.

Therefore, the plaintiff's claim of this case is accepted on the ground of the reasons.

The defendant of this case.

arrow