1. The Defendant (Counterclaim Plaintiff) against the Plaintiff (Counterclaim Defendant)

(a) The attached appraisal sheet among the lands listed in paragraph 1 of the attached list shall also be indicated.

Reasons

1. Facts of recognition;

A. The Plaintiff purchased each land listed in the separate sheet in the real estate auction procedure and completed the registration of ownership transfer on February 24, 2009.

The Defendant is the owner of a house of 350 square meters and its ground and a building of 377 square meters and a building of 357 square meters and a house adjacent to each of the above lands (hereinafter referred to as “C”).

B. The Defendant installed and owned a vinyl house and fence on the ground of D, and part of which was affected by each land listed in the separate sheet Nos. 1 and 2, as seen in the separate sheet Nos. 1 and 2.

(B) The Defendant, from the time of the Plaintiff’s purchase of each of the lands listed in the separate sheet No. 1 and paragraph (2) of this Article, occupied the portion partitioned by the aforementioned fence out of each of the lands listed in the separate sheet No. 1 to No. 11, 5, the attached appraisal of the land listed in the separate sheet No. 5 to No. 11, 2, 18, 19, and 1 among the land listed in the separate sheet No. 1, the attached sheet No. 42 square meters, and the attached appraisal of the land listed in the separate sheet No. 1, 2, 18, 19, and 1, connected each point in the separate sheet No. 1, 3 through 5, 11, 12, and 3, the attached sheet No. 49 square meters among the land listed in the separate sheet No. 2 of this case.

C. D and E lands owned by the Defendant are blind and each point of which is 2,3,12,13, 16, 17, 18, 18, and 2 of the attached Table Nos. 2, 3, 12, 16, 17, 18, and 2 of the attached Table Nos. 2, 3, 12, 13, 16, 17, 18, and 2 of the attached Table Nos. 2, and the attached Table Nos. 15, 16, 13, 14, and 15 of the attached Table Nos. 3 are the only way to connect F, which is a contribution to each land of

(hereinafter referred to as the “road” has passed the road of this case in order to make access to the road on D and E land. D.

From February 24, 2009 to July 28, 2017, part of each of the instant land and the rent for roads are KRW 2,213,400 in total.

July 29, 2017