(영문) 수원지방법원 안산지원 2014.03.25 2013고단3132
공문서변조등
Text

A defendant shall be punished by imprisonment for not less than eight months.

except that the execution of the above punishment shall be suspended for two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

The Defendant is a mine management director of Mongolia, a mine investment consulting firm in Mongolian U.S.

The Defendant, along with the Defendant’s father D, received USD 545,00,00, etc. as the name of KRW 545,00 from August 23, 2012 to October 16, 2013, in relation to the business of acquiring and operating a mine owned by G (G and one name H) located in Mongolia, from F that operates the said business for the purpose of railroad service in Korea.

With respect to the above mine transfer and mine drilling, Defendant and D obtained a demand to purchase two cargo trucks to transport drilling equipment from F (one truck of 4.5 tons at the market price of 16 million won, and 19.5 tons at the market price of 19.5 tons at the average of 16 million won) at the cost to purchase 2 cargo trucks (one truck of 19.5 tons at the market price of 16 million won). However, the above market price was not 19.5 tons of 33 million won at the market price, but the Defendant did not purchase 19.5 tons of 19.5 tons of 19.5 tons of 19.5 tons of 19.5 tons of 3 tons of 19.5 tons of 19.5 tons of 19.5 tons of 10 tons of 19.5 tons of 19.5 tons of 100 tons of 100,000 won of 19.

1. The Defendant, at the office of the Defendant located in Yongsan-gu Seoul Metropolitan Government at the end of January 2013, prepared the contents to be stated in each item of the export declaration completion certificate using a computer program screen document and printed out the contents to be stated in each item of the export declaration completion certificate and attached them to the export declaration completion certificate prepared in advance. The Defendant’s alteration of the official document in the column of the date of declaration is as follows: “2012/10/30; “J, K” in the buyer’s column; “2012/10/30” in the column of the date of inspection; “SERALN NADDDDDDD15T”; “3,000” in the unit price (USD); “33,000” in the unit price (USD) column; “30,500” in the column of report; “30,300,300,300,300,300,300,300,30,000” column;