Text
The Defendants jointly do so to the Plaintiff:
(a) deliver the buildings listed in the separate sheet;
B. 9,500,000 Won and April 20, 2020
Reasons
According to the overall purport of the theory of each entry and change in Gap evidence Nos. 1 through 7 (including each number number), the defendants entered into a lease contract between the plaintiff and the plaintiff on May 11, 2018 with respect to the building listed in the annexed list owned by the plaintiff (hereinafter "the building of this case"), with the lease deposit of KRW 10,000,000, monthly rent of KRW 1,500,000 (including value added tax), and the lease period from May 20, 2018 to May 19, 2020 (hereinafter "the lease contract of this case"), and thereafter, from around that time, the building of this case was used as the business office of the defendant limited to the defendant Eul, the name and personal information of the defendant, but there is no dispute between the plaintiff and the parties to the lease of this case.
Since the Defendants were in arrears for at least three occasions until August 2019, the Plaintiff notified the Defendants of the intention to terminate the instant lease agreement by September 30, 2019. The Defendants did not pay the overdue rent by the said deadline, and the fact that the Defendants did not pay the overdue rent by April 19, 2020 that the Defendants did not pay the overdue rent by the said deadline is recognized.
According to the above facts, the instant lease agreement was terminated by the Defendants’ failure to pay the Plaintiff the overdue charge until September 30, 2019.
Since the amount of unfair profit from the possession of the building of this case is presumed to be KRW 1,50,000 per month, which is the next rent under the instant lease agreement, the defendants delivered the building of this case to the plaintiff, and from KRW 19,500,000,000, a lease deposit of KRW 10,500,000, which the plaintiff recognized as being paid by the defendant at the time of the conclusion of the instant lease agreement, was deducted from KRW 10,000,000, and from April 20, 2020 until the completion of delivery of the building of this case.