logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원안산지원 2017.11.28 2015가단5538
설계비반환등
Text

1. The plaintiff (Counterclaim defendant)'s new architect office and the defendant (Counterclaim plaintiff) Gap.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. The following facts may be acknowledged in full view of the following facts: there is no dispute between the parties, or in full view of the entries of evidence Nos. 3 to 7, and witness B and witness C, and the purport of the entire pleadings:

On July 29, 2014, the Plaintiff entered into a design contract (hereinafter “first design contract”) for construction of an urban residential housing with the size of one underground floor and four stories above ground (2,956 square meters in total) on the 3,511 square meters above D prior to D, P, P, P, and P, P, P, P, the Defendant New Certified architect Office (hereinafter “Defendant Company”) (hereinafter “Defendant Company”) and the Plaintiff’s 3,51 square meters above D, and the main contents are as follows: (a) “A”, which is the contract document No. 3, the date of preparation, refers to “the date of July 31, 2014.”

- Contract amount of sound - Contract amount of KRW 49,170,000 (excluding value-added tax): Service period of KRW 4,00,000 (excluding value-added tax): From the date of transferring down payment to the date of permission for the service (Article 2): The calculation of basic design drawings, working design drawings, and other design documents necessary for the execution of the construction project, and the method of payment for the service cost for the preparation of other design documents necessary for the execution of the construction project: In principle, the time of payment and the amount to be paid shall be as follows, but may be adjusted through consultation between

Upon completion of construction permission of KRW 10,00,000 for a non-fixed-term service contract, 50% (excluding contract deposit) of the balance (not later than 10 days) of the balance of KRW 10,000 for a day (10,000 for a contract deposit) at the time of completion of construction permit of KRW 10,00,00 for each contract, respectively (excluding contract deposit and part payment) shall be provided for the settlement of total floor area (not later than 10 days for each contract deposit and part payment) in installments A, B, C, and D settlement of accounts (not later than 5,00) at the time of completion of each contract payment, respectively (excluding contract deposit and part payment) and the duty of good faith (Article 7): The plaintiff may, when the defendant company requests the following materials necessary for the performance of design work,

(2) The progress of the design and the construction permit.

arrow