(영문) 광주고등법원 2017.02.09 2016누4095
손실보상금증액
Text

1. Of the judgment of the court of first instance, the part against the plaintiff ordering payment shall be revoked.

The defendant on 785.

Reasons

1. Details of the adjudication on expropriation of this case

(a) project approval and public notice - Urban Planning Facility Construction Works - D Public Notice of Net City on July 31, 2014 and B Public Notice of Net City on February 23, 2015 - Project operator: Net City Mayor;

B. Decision to expropriate on June 24, 2015 (hereinafter “instant expropriation ruling”): - An appraisal corporation on August 10, 2015 - An integrated appraisal corporation, a joint appraisal corporation, a joint appraisal corporation - An appraisal corporation subject to expropriation and compensation for losses: Net City C-76 square meters (hereinafter “instant land”) owned by the Plaintiff, and a facility relocation cost for E-cafeteria operated by the Plaintiff. The detailed details of subject to expropriation and compensation for losses are 0,000, 308, 76 square meters and size of pipes as shown in the following table, 208, 80, 30,000 and 40,000, 30,000 and 760,000 and 40,000,000 and 20,000,000 and 20,000,000 and 30,000 and 76,000 buildings and 36,06,00 buildings and 36,0.

C. The court's 32.92 square meters and 17,765,280 square meters and 17,280 square meters and 27.92 square meters and 37.93,00 square meters and 21,33,520 buildings (house) 2.96 square meters and 37.96 square meters and 37.93,000 square meters and 21,33,520 buildings (house) 2.92 square meters and 32.92 square meters and 32.92 square meters and 17,765,200 buildings (stores) and 17.92 square meters and 17,280,000 square meters and 2.32.92 square meters and 19,752,000 square meters and 2.00 square meters and 200,000 square meters and 2000 square meters of cement-type 200,2000 square meters of cement 4.