Text
1. The Defendants shall jointly and severally pay to the Plaintiff KRW 99,275,00 and the interest rate thereon from September 24, 2015 to the date of full payment.
Reasons
If Gap evidence Nos. 1 and 2 points out the purport of the whole argument, it can be acknowledged that the defendants ordered the plaintiff to pay the construction cost stated in the order, as shown in the attached Form No. 1 and 2.
[Judgment of the Seoul Central District Court 2014Da16826, 17485 (Counterclaim), and Seoul High Court 2015Na2038420 (Counterclaim), and Seoul High Court 2038437 (Counterclaim), which is the appellate court] The Defendants are jointly and severally liable to pay to the Plaintiff the amount of KRW 99,275,00 and damages for delay calculated at the rate of 15% per annum from September 24, 2015 to the date of full payment, which is the following day when the duplicate of the complaint was served on the Defendants. Thus, the Defendants are jointly and severally liable to pay to the Plaintiff the amount of KRW 99,275,00 and damages for delay calculated at the rate of 15% per annum as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, which