Text
1. The plaintiff's claims against the defendants are all dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. Defendant B Housing Redevelopment Development and Improvement Project Association (hereinafter “Defendant Association”) obtained authorization on May 19, 2009 for a housing redevelopment improvement project, and implements a housing redevelopment improvement project (hereinafter “instant project”) with the size of 148,800 square meters in neighboring land (45,012 square meters) located outside Yongsan-gu, Changwon-si. The Defendant C is the head of the Defendant Partnership and the rest of the Defendants are the directors of the Defendant Partnership.
(hereinafter “Defendant C, etc.”). (B) The remainder of the Defendants except Defendant C, etc.
After obtaining the business authorization on May 19, 2009, the Defendant Union failed to bid three times for the selection of a contractor, and tried to select L as a contractor on February 2014, but the project was suspended due to the lack of gender.
C. On May 28, 2014, the Plaintiff was a corporation established for the purpose of real estate development business, etc., and entered into the instant business management service contract (PM) with the Defendant corporation (hereinafter “instant service contract”).
Article 2 (Scope of Business) It shall be limited to the site of the association for the redevelopment project of B Housing in the Jin-gu Seoul Special Metropolitan City, Jin-si, Jin-si, Jin-si, and when there is an increase or decrease in the area, it shall
Article 4 (Scope and Authority of Services)
1. Analysis of conditions of the location of the project site and analysis and formulation of a basic plan for the project;
6. To conduct affairs necessary for a proper development direction-setting and the selection of constructors; 10. to conduct affairs related to estimate examinations and the selection of constructors; and 18. to conduct affairs related to a contract;
1. All the expenses incurred by the Defendant Cooperative until the appointment of the contractor should be lent by the Plaintiff.
-the office operating expenses, the daily amount of KRW 15,000,000 per month (15,000,000) shall be deposited in the head of the Tong that is a partnership corporation by the 1
- Within two weeks after the conclusion of the contract, the Plaintiff deposited the total sum of KRW 800,000 in a bank account designated by the Defendant Union (200,000,000), and the total sum of KRW 800,000 (80,000) shall be one month.