(영문) 광주지방법원 2015.11.24 2015가단32481
물품대금
Text

1. The Defendant shall pay to the Plaintiff KRW 31,130,616 and the interest rate of KRW 15% per annum from July 10, 2015 to the day of full payment.

Reasons

1. Indication of claim: 45,130,616 won supplied from July 30, 2014 to February 9, 2015 at the construction site located in the building site located in the Namnam-gun, Namnam-gun, which was executed by the Defendant upon the Defendant’s request by the Defendant, shall be deemed to have been paid out of the price for the supply of the construction materials such as water, etc. 31,130,616 won, which was not paid (Article 208(3)2 of the Civil Procedure Act, the Defendant shall be served with the certified copy of the payment order, and the written objection shall be submitted, but the written objection submitted by the Defendant is only an objection against the payment order, and there is no indication of the Plaintiff’s assertion. Since the Defendant did not submit a written response, and thereafter, the Defendant did not appear at the date of pleading, it shall be deemed to have led to the confession of all the Plaintiff’s assertion under Article 150(3) of the Civil Procedure Act).

arrow