logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2018.11.15 2017가합53828
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 440,00,000 and the interest rate of KRW 15% per annum from June 30, 2017 to the date of full payment.

Reasons

1. The fact that the Plaintiff was awarded a contract from the Defendant for the construction of Yang-si, Yangju-dong 424-4, Yangju-si, Yangju-si, Yang-si, and that the Plaintiff commenced construction of the said Yang-si on May 28, 2015 and completed construction on May 13, 2016; and that the Plaintiff and the Defendant agreed on November 3, 2016 to pay the Plaintiff the remaining construction cost of KRW 440,00,000 (including additional tax) until March 15, 2017 is not a dispute between the parties.

Therefore, the Defendant is obligated to pay to the Plaintiff the remaining construction cost of KRW 440,00,00 and damages for delay calculated at the rate of 15% per annum from June 30, 2017 to the day of full payment, as the Plaintiff seeks.

2. It is so decided as per Disposition by the assent of all participating Justices on the ground that the plaintiff's claim is reasonable.

arrow