(영문) 대전지방법원논산지원 2015.03.26 2014가단2597
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 32,00,000 and the interest rate of KRW 20% per annum from November 9, 2014 to the day of complete payment.

Reasons

1. Indication of claim;

A. A. Around January 24, 2013, the Plaintiff entered into a contract with the Defendant for the installation of the 3kw solar power generation facilities to the Defendant (one million won of the intermediate payment, one million won of the remainder, and 2.5 million won of the remainder) and paid one million won of the down payment to the Defendant on the same day.

B. Around December 2, 2013, the Plaintiff entered into a contract with the Defendant for the installation of the solar power generation facilities on a contract with the Defendant for the installation of the 20kw solar power generation cost of KRW 44 million (15 million in the intermediate payment, KRW 20 million in the intermediate payment, KRW 9 million in the remainder, and value-added tax separate) and paid the Defendant the down payment KRW 15 million in the event of the Defendant’s breach of the contract, on December 4, 2013.

C. However, the Defendant is obligated to pay damages for delay at the rate of 20% per annum from the day after the delivery of a copy of the complaint of this case to the day of complete payment, inasmuch as the Defendant did not perform all the construction works under the above contract of this case.

2. Article 208 (3) 3 of the Civil Procedure Act: