logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대구지방법원 2016.10.21 2016가합205056
공사대금
Text

1. The Defendant’s KRW 589,30,000 as well as the Plaintiff’s annual rate of KRW 6% from May 1, 2015 to August 12, 2016, and the following.

Reasons

1. Construction work period (units: prime cost and value added tax) under the title of the claim, the date of the contract, and the title of the construction period (including unit construction) under the title of the claim, February 25, 2015;

3. 30. 113,300,000 - February 25, 2015, 2015 Newly constructed steel framed Corporation

3. 30. 173,800,00 3. 25 February 2015, 2015 - New steel framed Corporation

3. 30. 82,500,004. 4. 10 April 2015, 2015 additional steel framed Corporation

4. 30. 6,600,000 5. 10 April 10, 2015, 2015;

4. 30. 135,300,00 6. 10 April 10, 2015 - New Aggregate Construction Works at F site:

4. 30. 81,400,007 7. 10 April 10, 2015, 2015;

4. 30. 26,400,00 construction cost of KRW 619,30,000, the Plaintiff is obligated to pay the Plaintiff the unpaid construction cost of KRW 589,30,000 [the total construction cost of KRW 619,30,000] and delay damages for the construction cost of a factory located in Chungcheongnam-gun, Chungcheongnam-gun, the Plaintiff entered into a contract with the Defendant for the supply of sewage as indicated below. Since the Plaintiff completed the above sewage portion, the Defendant is obligated to pay the Plaintiff the construction cost of KRW 589,30,00 (the total construction cost of KRW 619,30,000 - the construction cost of KRW

2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts (Judgment without holding any pleadings due to the failure to submit a reply);

arrow