Text
1. The Defendant shall pay to the Plaintiff KRW 31,717,43 and the interest rate of KRW 15% per annum from October 19, 2017 to the day of full payment.
Reasons
1. Determination as to the cause of claim
A. If the purport of the entire pleadings is added to the statements in Gap evidence Nos. 1 through 4 (including a provisional number), it is recognized that the construction of reinforced concrete was contracted and constructed by C among the construction of new building built in B to be implemented by AD Industrial Development; the Plaintiff leased the construction of provisional materials, such as uniforms, etc. from November 21, 2016 to the above construction site from November 21, 2016; the Defendant at the time of the lease of the temporary materials; the lessee (a lease contract is stated as Sam Young-gu Co., Ltd., Ltd., which was the Defendant’s working company, but the company actually supplied with the Plaintiff’s temporary materials, was C); however, it is recognized that the unpaid rent was 46,717,433 won in total; while the Plaintiff had been paid the unpaid rent of KRW 15,00,000 during the lawsuit in this case.
B. According to the above, the Defendant is jointly and severally liable with C to pay to the Plaintiff KRW 31,717,43 and the damages for delay calculated at the rate of 15% per annum from October 19, 2017 to the day of full payment, which is the day following the delivery of a copy of the complaint of this case.
2. The plaintiff's claim for conclusion is reasonable, and it is so decided as per Disposition.