(영문) 광주지방법원 목포지원 2021.01.20 2017가단53171
선박 건조대금 청구의 소
Text

The defendant's 69,31,390 Won and its related 6% per annum from October 21, 2016 to January 20, 2021.

Reasons

(b) the facts of the basis;

A. On May 21, 2016, the Plaintiff entered into a contract with the Defendant to build a ship and deliver it to the Defendant (hereinafter “instant shipbuilding contract”).

The contents of the shipbuilding contract of this case are as follows (the part in which the body part is written): 122,00,00,000 tons of the contract amount of the shipbuilding yard contract of the main hull of this case, and 9.777, the main length of the FRP, in which the details of the joint purchase machinery and equipment portion (ship-supply goods): The total length of the vessel due to the construction of MM vessel is 122,000,000,000 22,350,000, 144,350, 1450, 144,350: M: M: * the project owner (Defendant) * the owner: (1) the Plaintiff (Plaintiff) the contract for the shipbuilding of the vessel is concluded; (1) the delivery of the vessel and the location of the vessel are to be extended at the time of delivery of the vessel to the Plaintiff’s place of business by July 29, 2016; and (2) the above extension is to be extended at the time of the date.

(b) 6. 6. Repayment - Except as provided in the preceding Article when completion of this construction is not completed within the period, Eul shall pay to Gap an amount equivalent to 2/100 of the construction amount per day delayed.

B. On May 22, 2016, the Plaintiff received down payment of KRW 40,000,000 under the instant shipbuilding contract from the Defendant.

(c)

The Plaintiff built a name C, hull material FRP, and total tonnage of 11 tons under the instant shipbuilding contract (hereinafter “instant vessel”), and delivered the instant vessel to the Defendant on October 3, 2016.

(d)

The defendant completed the registration of ownership on October 21, 2016 with respect to the instant vessel.

【Unsatisfy-founded facts, Gap evidence Nos. 1, 3, and 19, witness D, and E, respectively.