1. The Defendant: KRW 66,721,00,07, and the Plaintiff’s annual rate from February 13, 2018 to December 19, 2018, respectively.
Reasons
1. Facts of recognition;
A. On April 28, 2017, the Defendant entered into an urban comprehensive development project agreement with the Chinese People's Government.
D’s investment in approximately 10 billion People’s Republic of Korea in approximately 3,60,000 square meters, with the aim of constructing and comprehensively developing Class 5 hotel, Korea’s sex-type general hospital, international school, high-class net town, large-class discount store, etc., and at the time of the preparation of the contract, the name of the contract is the defendant, and E’s representative director E puts his/her seal on behalf of the defendant in the contract.
B. The plaintiff has participated in the process of concluding the above project contract and concluded a service contract for the establishment of master plans and the feasibility review of the project after the conclusion of the above project contract, and the defendant's request for service duty to the plaintiff is not the defendant but F. However, as seen above, considering the fact that the party to the project contract is the defendant under the contract and the plaintiff received the report on master plans prepared by the plaintiff, it is reasonable to view that the plaintiff's request for service duty is the defendant.
At the request of the Committee, the work of preparing the master plan began to be performed.
C. Since then on June 7, 2017, the Plaintiff, Defendant, G, and H alleged that the date of the written contract preparation is June 15, 2017. However, considering the overall purport of pleadings in the video of evidence No. 29, the date of the written contract preparation is recognized as June 7, 2017.
The service period for China D Complex Development Project Master and Project Feasibility Review Services shall be from the commencement to July 31, 2017 (from the date of the final performance submission to the date of the final performance, in line with H proceeding schedule), the total contract amount of KRW 350,000,000, and advance payment of KRW 20% of the contract amount shall be paid within 15 days after the contract, and 40% shall be paid within 15 days after the submission of the master plan.