(영문) 인천지방법원 2013.11.27 2011가단110295
양수금
Text

1. The Defendant’s KRW 32,537,065 as well as 6% per annum from December 1, 2011 to November 27, 2013 to the Plaintiff.

Reasons

The defendant, on September 30, 2010, concluded a contract with the Sido Comprehensive Construction Co., Ltd. (hereinafter referred to as the "Seodo Construction") for the construction of a ground warehouse and a factory (hereinafter referred to as the "instant construction") in Nam-gu Incheon Metropolitan City, Nam-gu, Seoul (hereinafter referred to as the "Seodong-gu Construction") with the construction cost of KRW 1.2 billion (excluding value-added tax) and the construction period from October 9, 2010 to December 30, 2010.

On December 2, 2010, the non-party company subcontracted the electrical construction part of the instant construction to the Plaintiff as KRW 130 million (excluding value-added tax).

On June 6, 2011, the Defendant and the non-party company calculated the construction cost of the non-party company 1.325 million won, including value-added tax (i.e., the contract price of KRW 1.32 billion, KRW 1.65 million, additional construction cost for automatic text - KRW 1.6.5 million, and the amount calculated by deducting the above amount from the contract amount of KRW 1.45 billion, KRW 2.5 million, KRW 2.5 million, KRW 2.5 million, KRW 2.5 million, KRW 2.5 billion, KRW 2.5 billion, KRW 2.5 billion, KRW 2.5 billion, KRW 2.6 billion, KRW 2.5 billion, KRW 2.5 billion, KRW 2.8 billion, KRW 2.5 billion, KRW 2.6 billion, KRW 2.5 million, and KRW 2.8 billion, KRW 2.5 billion, KRW 2.5 million, and KRW 2.5 billion, and KRW 2.5 million, respectively.

(hereinafter “The First Settlement Agreement”). On August 1, 201, the Defendant and the non-party company obtained the remainder of KRW 18,285,50,00 from deducting the Defendant’s direct payment of KRW 113,714,450,00 ( KRW 38,60,000, Tae Young-young, Inc., Tae Young-young, Inc., Ltd., 38,600,000, KRW 20,889,450), on behalf of the Plaintiff, to the subcontractor at KRW 32,20,000,000 in the remainder of the construction cost prior to the second settlement agreement. Nonparty 18,285,550, which was the remainder of the construction cost prior to the second settlement agreement