logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2017.04.06 2016가단5235339
연출료
Text

1. The Defendant’s KRW 26,00,000 as well as the Plaintiff’s annual rate of KRW 6% from July 17, 2015 to September 12, 2016.

Reasons

1. On June 13, 2014, the judgment on the cause of the claim was made between the Plaintiff and the Defendant running film production business, etc.: (a) the Defendant entered into a contract for supervision of production under B (A) and paid KRW 120 million to the Plaintiff in return for the performance of supervisory duties; (b) the Defendant agreed to pay KRW 36 million to the Plaintiff within seven days from the date of conclusion of the contract; (c) the intermediate payment of KRW 48 million within seven days from the date of commencement of filming; and (d) the remainder of KRW 36 million within seven days from the date of completion of filming; and (e) the fact that the Plaintiff’s film release and photographing ends on July 9, 2015 is deemed to have been led to the failure of the Defendant to clearly dispute, and that the Plaintiff received KRW 10 million from the Defendant the said down payment, intermediate payment, and remainder.

According to the above facts, the defendant is obligated to pay to the plaintiff the remainder amount of 26,00,000 won (=the remaining amount of 36,00,000 won - the amount of 10,000,000 won) and damages for delay calculated at each rate of 15% per annum under the Commercial Act from July 17, 2015 to September 12, 2016, which is obvious from the record that the delivery date of the original copy of the payment order in this case is the delivery date of the original copy of the payment order in this case, and from the next day to the date of full payment.

2. It is so decided as per Disposition by the assent of all participating Justices on the ground that the plaintiff's claim of this case is reasonable.

arrow