(영문) 광주지방법원 순천지원 2013.05.15 2013고정132
사기
Text

Defendants shall be punished by a fine of KRW 6,500,000.

In the event that the Defendants did not pay the above fine, 50.

Reasons

Punishment of the crime

1. The “Support Project for Re-Support Facilities for Village-Based Residents” promoted the “Support Project for Re-Support Facilities for Village-Based Residents” with the content of the local government’s subsidy to increase the added value of farmers around 2009 for each Si/Gun.

The total project cost shall be KRW 100,000,000, and 70% among them shall be Dovina, 20% shall be Gunvina, and 10% shall be appropriated for self-payment of the person subject to the project.

On the other hand, Defendant A, who was in office as the head of the E Village E in Jeonnam-gun, applied for the establishment of the “E Village Spool Spool Factory” in the name of Women’s Association of the above Village (F) around September 2009 for the recruitment of persons eligible for the above project.

2. The facts constituting the crime committed by Defendant A and the above female association did not have any intention or ability to bear 10,000,000 won out of the total project cost, even if they were selected as the subject of the above support program.

Nevertheless, Defendant A, who is the representative director of G Construction, offered the payment of KRW 10,000,000 for the actual construction cost under the condition that he subsidized G Construction. However, the actual construction cost is KRW 86,00,000,000 for Defendant B, who is the representative director of G Construction, and, as if he had carried out the construction work, the High Reconstruction-gun Office offered to receive the payment of KRW 90,00,00 for the submission of the relevant documents by falsity.

Defendant

A around January 20, 2010, when filing an application for a subsidy at the food distribution department and office of the Gosong-gun, Gosong-gun, Gosong-gun, Gosong-gun, and submitted a copy of the deposit passbook in the F name deposited in KRW 10,000,000 as if it were self-paid by Defendant A and the above women's association, and the above women's association was selected as the recipient of the subsidy on March 17, 2010.

Afterward, the Defendants entered into a contract with the total cost of construction of a salted plant in accordance with the above business plan to KRW 100,000,000, and the relevant documents, such as tax invoices, as if the construction was conducted, are false.