(영문) 서울중앙지방법원 2018.04.25 2017가합536918
손해배상(기)
Text

1. As to KRW 306,538,619 and its KRW 210,00,000 among the Plaintiff, the Defendant shall be annually from February 20, 2009 to June 5, 2017.

Reasons

1. Basic facts

A. The Minister of Construction and Transportation (A) on March 3, 1998, extended B roads from Sungnam-si, Sungnam-si, to D on March 3, 1998 (hereinafter “instant road project”).

(2) At the time of enforcement, Songpa-gu Seoul E-gi (hereinafter “instant land”) owned by the Plaintiff was incorporated into the instant road project zone.

3) The Defendant entrusted with the instant road project by the Republic of Korea with the instant road project implementation by the Republic of Korea (amended by Act No. 6656, Feb. 4, 2002; hereinafter “Public Special Act”) is the Act on Special Cases Concerning the Acquisition of Land for Public Use and Compensation for Loss

(2) On February 20, 199, the Minister of Construction and Transportation, on the instant land on February 20, 199, completed the registration of ownership transfer under the name of the Republic of Korea (Defendant in the custody office) on the ground of “acquisition of public land on February 9, 199,” and around that time, paid 159,840,000 won (540,000 square meters per square meter x 296 square meters) to the Plaintiff as compensation for the acquisition of the instant land through consultation. (b) The process of implementing the F Housing Site Development Project (1) on December 6, 2002, the Seoul Special Metropolitan City Urban Development Corporation (a trade name after the alteration: Seoul Housing Corporation; hereinafter “Seoul Housing Urban Corporation”) designated and announced the housing site development area of 614,000 square meters including the instant land as a F-dong housing site development area.

2) On October 6, 2003, the Seoul Special Metropolitan City Mayor approved and publicly announced a development plan for the F Housing Site Development Project (hereinafter referred to as “instant housing site development project”).

(3) On December 26, 2003, the Seoul Special Metropolitan City Mayor approved and publicly announced the development plan and implementation plan of the housing site development project of this case, and the land of this case is included as a site for multi-family housing.

4. The Mayor of Seoul Special Metropolitan City on November 8, 2007 housing site development business of this case.