(영문) 수원지방법원 성남지원 2017.03.15 2016가단219067
공사대금
Text

1. The Defendant: KRW 13,432,945 to the Plaintiff; KRW 69,427,055 to the Intervenor succeeding to the Plaintiff; and each of them on December 7, 2016.

Reasons

On October 19, 2015, the Plaintiff entered into a contract for construction works with the Defendant at KRW 170,500,000 with respect to electrical construction among the Corporation A’s Ground B Hospital in Seo-gu, Seo-gu. On December 18, 2015, the Plaintiff entered into a contract for additional construction works at KRW 5,610,00 with respect to the said construction works. The Plaintiff completed the said construction works, and received KRW 93,250,000 from the Defendant. The Plaintiff transferred KRW 69,427,05 of the claim against the Defendant against the Intervenor on August 12, 2016 to the Plaintiff’s successor on August 24, 2016. According to the Plaintiff’s application form for additional construction works at KRW 5,50,000 with respect to the said construction works, the Plaintiff’s transfer notification to the Defendant on August 24, 2016, and the Plaintiff’s transfer notification to the Plaintiff’s heir on KRW 25145,251, and the Plaintiff’s allegation.

Therefore, the claims of the plaintiff and the plaintiff succeeding intervenor are justified, and they are decided as per Disposition by admitting them.

arrow