(영문) 대전지방법원 2015.06.25 2015가단11653
대여금
Text

1. The defendant shall be the plaintiff.

(a) 24% per annum from January 1, 2014 to March 31, 2015 for KRW 170 million.

Reasons

1. Indication of claim;

A. On May 31, 2013, the Defendant: (a) borrowed KRW 170 million from the Plaintiff on December 31, 2013 at the rate of 12% per annum; and (b) prepared and issued a certificate of borrowing that the Plaintiff shall pay 24% interest per annum to the Plaintiff on the last day of each month when the maturity expires; and (c) around March 2015, the Defendant repaid KRW 90 million by deposit.

B. Therefore, the Defendant is obligated to pay to the Plaintiff the damages for delay calculated by the rate of 24% per annum from January 1, 2014, the following day following the due date for repayment of the above KRW 170 million to March 31, 2015, and the damages for delay calculated by deducting the above KRW 90 million from the above KRW 170,000,000 (=170,000 won - KRW 90,000) and the remaining principal amount of KRW 80,000 from the above KRW 170,000 and KRW 80,000,000,000 from April 1, 2015 to the day of full payment, from the day following the day when repayment takes effect by the above deposit.

2. Judgment deeming the confession as the basis (Article 208 (3) 2 of the Civil Procedure Act).