logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울서부지방법원 2018.11.02 2018나36100
보험금
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1...

Reasons

1. The reasoning of the judgment of the court of first instance cited in the judgment of the court of first instance is as follows: (a) “from April 7, 2015 to July 7, 2015, the date on which 60 days elapsed from the date on which the request was made,” and (b) the part on “3. Judgment” from April 2 to 9, 1, 2015 to the part on “3. Judgment” from the date on which the request was made under the main sentence of Article 420 of the Civil Procedure Act shall be cited

2. The following circumstances acknowledged as a whole by considering the overall purport of arguments as to Gap evidence Nos. 2, 7, 12, Eul evidence Nos. 3 through 6, and 8 through 12. The term of the insurance contract of this case is as to the meaning of the occurrence of sales claim (Article 9(1) of the Terms and Conditions), settlement date (Article 10 of the Terms and Conditions), and insurance accident (Article 11 of the Terms and Conditions), but the meaning of delay of performance is not separately provided for the meaning of delay of performance and it is not clear that the subscription form of the insurance contract of this case (Evidence No. 12) does not separately provide for the meaning of delay of performance at the time of the preparation of the subscription form of the insurance contract of this case or the conclusion of the insurance contract of this case, and it does not appear that the plaintiff explained about the exact meaning or criteria of delay of performance from the defendant at the time of the conclusion of the insurance contract of this case (the meaning of delay of performance and standard itself are not set up before the insurance contract of this case No. 294.

Article 11 subparagraph 4 of the terms and conditions of the insurance contract of this case on 90 days, which is the settlement period for the commercial construction.

For the purposes of this item.

arrow