logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원부천지원 2015.07.08 2013가합10535
매매대금
Text

1. The Defendant’s KRW 26,894,053 for the Plaintiff and KRW 5% per annum from January 11, 2014 to July 8, 2015.

Reasons

1. Basic facts

A. The Plaintiff and the Defendant entered into a sales contract for land and factory between the Plaintiff and the Defendant on August 201, 201, and each land indicated in the separate sheet to the Defendant (hereinafter “each land of this case”).

) Each land listed in paragraphs 1 through 6 of the attached list and the attached list (hereinafter referred to as “instant factory site”).

(2) The Plaintiff concluded a sales contract to sell the total amount of a factory to be newly built at KRW 3,00,000 (hereinafter “instant sales contract”) (hereinafter “instant sales contract”).

(2) In concluding the instant sales contract, the Plaintiff and the Defendant agreed to pay the down payment of KRW 150,000,000,000, out of the sales price, until September 1, 201, and the intermediate payment of KRW 1,000,000,000, after completing the civil engineering works on the instant factory site, with the loan granted from the bank, and the remainder of KRW 1,950,000,000, within 15 days after the completion of the factory to be newly constructed on the instant factory site.

3) After that, the Plaintiff received KRW 150,00,000 from the Defendant on September 6, 201, and KRW 100,00,00 as part of the intermediate payment around February 2, 201, respectively. (b) The Plaintiff concluded a contract for each construction contract between the Plaintiff, the Defendant, and the Cheongpo-Tech Co., Ltd. (hereinafter “Cheongpo-Tech”) on February 2, 201 with the Cheongpo-Tech Co., Ltd. (hereinafter “Cheongpo-Tech”), and concluded a contract for the construction work of the instant factory site with the terms that the construction work cost of the instant factory site is KRW 300,00,000 (excluding value-added tax) and the construction period from February 1, 2012 to May 31, 2012.

2) After that, the Plaintiff entered into a contract for construction works with the Cheongyang on March 12, 2012, under which the construction work for constructing a new factory of 600 square meters on the instant factory site was determined as the construction cost of 540,000,000 won (excluding value-added tax) and as the construction period from March 12, 2012 to April 30, 2012, and the construction contract was to be awarded to Cheongpo-do. 3) Meanwhile, an additional construction work was required while the new factory construction work in the instant case was being carried out. Accordingly, the Defendant was on March 27, 2012.

arrow