Text
1. The Defendant shall pay to the Plaintiff KRW 22,00,000 and the interest rate of KRW 15% per annum from July 27, 2016 to the day of complete payment.
Reasons
Around October 29, 2015, the Plaintiff entered into an agreement investment contract with the Defendant and paid KRW 30,000,000 to the Defendant, but the Defendant’s business was not well run, and the Defendant decided to return KRW 30,000,00 to the Plaintiff. However, even though the Plaintiff returned KRW 8,00,000 among them, the Plaintiff did not refund KRW 22,00,000 to the Plaintiff, there is no dispute between the parties.
Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 15% per annum from July 27, 2016 to the day of full payment, which is the day following the delivery of the original copy of the instant payment order, sought by the Plaintiff, from July 27, 2016 to the day of full payment.
Therefore, the plaintiff's claim shall be accepted for the reasons and it is so decided as per Disposition.