Text
1. The Defendant’s KRW 22,723,00 for the Plaintiff and 6% per annum from July 31, 2015 to September 30, 2016.
Reasons
1. Basic facts
A. The Plaintiff is a construction business operator, and the Defendant is a company running a camping house.
B. On June 12, 2015, the Plaintiff completed on July 30, 2015, the entire construction work including additional construction work equivalent to KRW 13,500,000 (hereinafter “the instant construction work”) awarded a contract with the Defendant for KRW 69,00,000 for the amount of KRW 13,50,000 from the Defendant’s “a tent construction work and a tent construction work (hereinafter “the instant construction work”).
C. After the construction of the instant construction, an accident that damages the exterior wall of the Doglar, which was built by the Plaintiff on the strong wind, was caused by tearing the tear and exceeding the support cost of the iron agents.
The Plaintiff did not receive KRW 30,500,000 from the Defendant’s payment of the said construction cost.
[Ground of recognition] The fact that there is no dispute, Gap's 1 through 3, 5, 6, Eul's 3, the purport of the whole statement or video, or pleading
2. According to the above findings of determination as to the cause of the claim, the Defendant is obligated to pay the Plaintiff the unpaid construction cost of KRW 30,500,000, including the additional construction cost, and the delay damages therefor, unless there are special circumstances.
3. Judgment on the defendant's assertion
A. Defendant’s assertion 1) The Plaintiff did not complete the construction work. 2) The Plaintiff was defective in the construction work, and the Plaintiff incurred extended damages due to such defect, and thus, the Plaintiff is obligated to compensate the Defendant for the extended damages due to the Defendant’s liability for damages in lieu of defect repair and the incomplete performance. Accordingly, the Plaintiff’s claim for damages against the Plaintiff’s claim
B. The criteria for distinguishing between the failure to complete the construction work from the failure to complete the construction work, and the failure to complete the construction work of a new building, are deemed to have completed the construction work if the construction has not completed the last process scheduled to be interrupted during the construction work. However, the construction has been completed once it has completed the last scheduled work.
Part of structure.