(영문) 서울고등법원 2015.12.18 2014나2021371
재단채권확인의소
Text

1. Upon receiving a modified claim from the trial court, the Defendant shall pay to the Plaintiff KRW 150,00,000 and its amount from November 24, 2015.

Reasons

1. The following facts do not conflict between the parties, Gap evidence 1 (the same shall apply to the evidence No. 4), 2 (the same shall apply to the evidence No. 5), 3 (the evidence No. 2-1 of the evidence No. 2 of the evidence No. 3), Gap evidence No. 4, 5 (the evidence No. 1-4, and 2-2 of the evidence No. 5 of the evidence No. 5 of the evidence No. 1 of the Act are the documents extracting part of the evidence No. 5 of the evidence No. 7 of the evidence No. 1 of the Act), Gap evidence No. 9-1 and 4 of the Act No. 11, Gap evidence No. 12, Gap evidence No. 14, 15-1, 16-1, 10, 17-2, and 2-3 of the evidence No. 1, Gap evidence No. 2 of the Act No. 2 of the evidence No. 5 of the Act No. 1, No. 3 of the evidence No. 2 of the evidence No. 2 of the evidence No. 3 of the evidence No. 17

A District Land Readjustment Project and Construction Contract Conclusion 1) The Plaintiff was one thousand square meters of the land of 1,437,841 square meters in Ulsan-gu and E, Ulsan-gu, which was enforced from around 1998, but the said area was modified on April 1, 1999 (hereinafter “instant project district”).

(2) The land readjustment project of this case (hereinafter referred to as the “land readjustment project of this case”)

(2) On August 28, 1998, the Plaintiff is the project implementer of the project. 2) The Plaintiff acting on behalf of the Plaintiff for the project implementation of the land readjustment project of this case, including the project implementation work of this case, the preparation and approval of the design plan, the construction work execution and removal compensation work, etc., with respect to the land readjustment project of this case, including that the land rearrangement project of this case was contracted by the Plaintiff.