logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산지방법원 2018.08.28 2016가단300410
공사대금
Text

1. The Defendant’s KRW 23,827,772 as well as the Plaintiff’s annual rate from January 12, 2016 to August 28, 2018, and the following.

Reasons

1. Facts of recognition;

A. On July 29, 2014, the Plaintiff entered into a contract for construction works (hereinafter “instant contract”) with the Defendant, and Busan-gu Seoul-gu Seoul-gu Seoul-do-based neighborhood living facilities (hereinafter “instant construction works”) with respect to the construction cost of KRW 6.5 million (including value-added tax; hereinafter the same shall apply). The construction cost of KRW 55 million with advance payment, KRW 30 million within 10 million after the contract was concluded, and the remainder is paid within 60 days after completion, and the construction period was determined from August 15, 2014 to December 31, 2014 (hereinafter “instant contract”).

B. On November 17, 2014, D, where the Plaintiff was an internal director, concluded a contract with the Defendant and the E-bank head in the name of the E-bank (hereinafter “E-bank head”), setting the construction cost of KRW 30 million with respect to the closing work of outer walls during the construction. The Defendant wired KRW 20 million to the E-bank head in the name of D on November 20, 2014.

C. On December 20, 2014, D and the Defendant, “Defendant shall pay the remainder of KRW 165 million out of the balance of the contract for the work to 220 million to February 10, 2015, and shall pay the remainder at the same time as the certificate of completion upon completion of the work. The contract air does not separately calculate the completion date due to the interior interior interior interior interior interior interior interior interior interior interior interior interior interior installation (such as the change from the system windows to the general window, each interior temperature control is changed to the integrated management period, the electricity, communications, and the fire fighting corporation’s construction through consultation between the Defendant and the Defendant). On December 30, 2014, the Defendant shall pay the remainder of KRW 10,000,000,000,000 to KRW 430,000,000,000,000,000,0000,000,000,000).

On January 22, 2015, the Plaintiff is the Defendant.

arrow