1. The defendant's claim for construction cost against the plaintiff was made by the Daegu District Court for Permanent Residence Branch of the Daegu District Court (2015j218).

Reasons

1. A claim based on the payment order in the payment order in the case of a claim for construction price payment against the Plaintiff at the Daegu-dong District Court, the Daegu-dong District Court, 2015j218, against the Plaintiff, was extinguished due to the Plaintiff’s repayment of KRW 107,330,00 to the Defendant on March 10, 2016, and thus, a non-permission of compulsory execution based on the above payment order is sought.

2. Article 208(3)1 of the Civil Procedure Act of the applicable provisions of Acts (a judgment without pleadings, and the defendant submitted a written answer to the effect that all facts constituting the grounds for the claims are confessiond);