Text
1. The defendant's appeal is dismissed.
2. The costs of appeal shall be borne by the Defendant.
Purport of claim and appeal
1..
Reasons
1. The reasoning of the judgment of the court of first instance is as follows. The defendant's assertion added by this court is identical to the reasoning of the judgment of the court of first instance, except for the judgment of Paragraph 2 as to the assertion added by this court. Thus, it is acceptable to accept it as it is in accordance with the main sentence
2. The two pages 12 "D" is raised into "U and two parcels."
2. The 2nd 13th Myeon (hereinafter referred to as the "G") shall be raised to the "R".
The 2nd parallel 17th parallel 17th parallel to 3th parallel parallel 4th parallel parallel are as follows:
“1) On December 16, 2013, Defendant, E, F, and G entered into a contract for construction works with I (hereinafter “I”) on June 30, 2014 for the completion of the project for solar power plant construction works (the contract amount is the same as the contract amount, although each corporation entered into an individual contract, and the remaining contract amount is the same) and I started construction works around that time.
2) On March 21, 2014, the decision of commencing the rehabilitation procedure was rendered to I on March 21, 2014 (the Seoul Central District Court Decision 2014 Ma55, hereinafter the rehabilitation company and manager are not distinguished), the Defendant, E, F, and G entered into a contract on the alteration of the completion date of the rehabilitation procedure into on September 30, 2014 with I on July 18, 2014; 3) I notified the Defendant, etc. on March 5, 2015 that the contract for the construction work was terminated on February 25, 2015 on the ground that payment was not made.
The 3th 6th 8th 7th 6th 7th 6th 6th 6th 8th 9th 9th 9th 9th 9th 9th 9th 1st 1st 3th 3th 3th 14th 3th 5th 5th 5th 1st 5th 5th 1st 5th 201 as follows: “The completion of development activities for the entire solar power plants of the Defendant, etc., and approval for use of buildings for mushroom farming companies, which are the lower structure of solar power plants, was completed.”
[Grounds for Recognition] Unstrifed Facts, Gap 1, 6, 11, 43 evidence (including branch numbers if any); hereinafter the same shall apply)
Category B 1, 14, 15, 21.