Text
1. All of the plaintiffs' claims are dismissed.
2. The costs of lawsuit are assessed against the plaintiffs.
Reasons
1. Basic facts
(a) On November 3, 1983, 1C entered into a loan agreement, etc., the same month after purchasing real estate from D as stated in the separate sheet;
4. On May 2, 1984, after completing the registration of ownership transfer, purchased the 4 real estate listed in the separate sheet from the defendant on May 2, 1984 (hereinafter referred to as the "fourth real estate, etc."), and purchased it from the defendant, and then purchased it.
7. The registration of ownership transfer shall be completed.
C donated the third real estate to E on May 6, 1998.
2) On October 29, 1983, C newly constructed a house (area 21.42 square meters) with a building permit granted on the ground of the real estate on May 3 through 5, 1985. On May 9, 1985, C newly constructed the relevant building with a building permit granted on the ground of the first floor underground and the first floor size of the ground. 3) On January 22, 2002, Jeju and Jeju Real Estate 1 (the registration of ownership was completed in the Defendant’s name on November 19, 2001) with the purpose of using a parking lot of 49 square meters for the site, rent, annual amount of rent, KRW 1,326,140, and loan period until December 31, 2004, C concluded a lease agreement with the State property until December 31, 2004.
4) On March 10, 2005, C requested the renewal of the loan agreement on 49 square meters among the real estate 1, and entered into a loan agreement on State property again with Jeju-si on March 10, 2005. Since then C delayed payment of some of the loan charges in 2005, Jeju-si decided and notified the collection of late payment charges (2,50 won) on May 19, 2005. (b) On the application of the F Co., Ltd. F, Ltd. (1) on June 16, 2009, H purchased the said real estate on January 5, 2010 during the voluntary auction procedure commenced with Jeju District Court G on June 16, 2009.
2. On September 20, 201, the Korea Asset Management Corporation notified H of the imposition period for the first and second real estate adjoining to the third or fifth real estate in advance from January 5, 2010 to October 10, 201, however, H of the first and second real estate in advance was dissatisfied with the business commencement date on April 8, 201.
The Korea Asset Management Corporation shall be H.