(영문) 부산지방법원 2015.06.10 2014가합3781
공사대금
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 3,786,057 to the Plaintiff (Counterclaim Defendant) and its related amount from August 12, 2014 to June 10, 2015.

Reasons

Basic Facts

On August 5, 2013, upon introduction by C, the representative director of the Geum River Construction Industry Co., Ltd. (hereinafter “B”), the Defendant awarded a contract to the Geum River Construction Industry Co., Ltd. (hereinafter “ Geum River Construction Industry”) for D operation, Nadong Construction Project (hereinafter “instant building,” and the construction thereof was referred to as “instant construction”). Three contracts were made between the Defendant and the Geum River Construction Industry as listed below.

(2) On August 28, 2013, on August 28, 2013, the date of preparation of each contract agreement between the Defendant and the Geum River Construction Industry (Evidence 1-1-2 (Evidence 1-2 (Evidence 2 (Evidence 4-2 (Evidence 4-2 and 3) of Section 2 (Evidence 2) of Section 3 of each contract signed between the Defendant and the Geum River Construction Industry, including the value-added tax of KRW 60,00,00,000,000 and value-added tax of KRW 30,00,00,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,00,000,000,00,00,000 won

Each contract agreement between the defendant and the plaintiff (No. 7, No. 4-2) is signed by Section 2 (No. 5, No. 5-2, No. 5-2), written by Section 3, No. 4, written by Section 3, and written by Section 2, written by Section 3, and No. 4, written by Section 2.

(A) Evidence 6-1) Article 4 (Evidence 6-2 of the Contract Form 5 (Evidence 6-2 of the A) Article 4 (Evidence 15 of the Contract Form), the scope of construction work, Dong, Dong, Dong, Dong, Dong and Dong, and Nadong on October 9, 2013 on October 9, 2013, October 9, 2013, 2013; the construction period from October 9, 2013 to November 30, 2013 to October 30, 2013; and the construction amount from October 30, 2013 to October 30, 2013 to October 30, 2013 to October 31, 2013 to October 31, 2013 to October 31, 2013; and