(영문) 대전지방법원천안지원 2015.10.07 2015가단9505
공사대금
Text

1. The Defendant’s KRW 25,00,000 as well as the Plaintiff’s annual rate of KRW 6% from December 28, 2013 to August 3, 2015.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment without holding any pleadings (Article 208(3)1 and Article 257 of the Civil Procedure Act): Provided, That the Plaintiff’s claim for delay is accepted only within the extent recognized under the main sentence of paragraph (1) of the Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings (the statutory interest rate shall be changed from October 1, 2015 to 15% per annum; the statutory interest rate shall be changed from October 1, 2015 to 20% per annum; the statutory interest rate shall be 20% per annum until September 30, 2015 and the annual interest rate shall be applied from October 1, 2015 to 15).