공사대금
1. The Defendant’s KRW 809,600,000 as well as 6% per annum from September 23, 2016 to May 23, 2017 to the Plaintiff.
1. Determination as to the cause of claim
A. 1) On July 19, 2016, the Defendant awarded a contract to the Plaintiff for the interior and electric facilities construction of “C” (hereinafter “instant contract”).
The details of the instant contract are as follows.
Construction contract documents
1. Construction name: C;
2. Construction site: D (E building underground floor);
3. Date of commencement: July 19, 2016.
4. Date scheduled for completion: August 30, 2016.
5. Contract amount: Amount of KRW 1,619,200,000 (including value-added tax); and
8. A completed amount: August 16, 2016 (20% or more of the total construction amount, 50% or more of the balance, 45% or less after completion of 50%) 13. Other matters: see Article 22 of the General Conditions of the Contract for Construction Works [Article 22 [Article 22] [Article 22 of the General Conditions of the Contract for Medium-Term Construction Works [Article 22] (Article 22 of the Contract for Medium-Term Construction Works] (Article 22 of the "B" (referred to as the "Plaintiff" in this Schedule) may request an inspection of the completed portion. In this case, the "A" (referred to as the "Defendant" in this Schedule) shall conduct an inspection without delay and notify the "B" of the results thereof, and shall be deemed to have passed the inspection if
(2) The completed portion shall be calculated according to the unit price of the calculation sheet under subparagraph 8 of Article 2.
Provided, That where there is no calculation statement, the agreement between "A" and "B" shall be calculated according to the construction progress ratio.
(3) "A" shall be paid to "B" the amount completed according to the details inspected within 14 days from the date of completion of the inspection.
(A) Article 39 (Special Agreement) Other matters not provided for in this Agreement may be determined by a separate special agreement between A and B.
1. The construction amount shall be calculated by plane;
(320 square)
2. The construction amount shall be one hundred thousand won per square meter.
(b)
5. A shall pay B 20% or 50% of the total construction cost (cash) within 16 August 2016.
The balance shall be 50% in full within 45 days after completion.