beta
(영문) 제주지방법원 2019.01.22 2018가단52213

대여금

Text

1. The Defendants are jointly and severally liable to the Plaintiff for 45 million won and the interest rate of 20% per annum from December 31, 2007 to the day of complete payment.

Reasons

1. The Plaintiff, on May 29, 2007, lent the amount of KRW 45 million to Defendant B on December 30, 2007, with a maturity of KRW 20% per annum on December 30, 2007, and the delay damages rate of KRW 20% per annum. At the time, Defendant C, at the time, has guaranteed the Plaintiff’s joint and several debt of Defendant B’s above loan. There is no dispute

Therefore, the Defendants are jointly and severally liable to pay to the Plaintiff the agreed damages for delay calculated at the rate of 20% per annum from December 31, 2007 to the day of full payment, which is the day following the due date of the above loan.

2. In conclusion, the plaintiff's claim against the defendants is accepted in its reasoning, and it is so decided as per Disposition.