배당이의
1. All of the plaintiff's claims are dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. On February 24, 2014, Plaintiff 2 and Nonparty 2 were to have a loan claim against Nonparty 3 Co., Ltd., Ltd. (the first one was Co., Ltd. D, as of May 9, 2014; hereinafter the same shall apply) and applied for voluntary auction to this court B to realize the collateral. The Plaintiff acquired the collateral security claim against Defendant 2, and participated in the distribution procedure by transfer of the collateral security claim of the above bank, and ② the Defendants were to have been distributed out of the total amount of KRW 92,03,473 on August 23, 2017 to KRW 100,000, KRW 680, KRW 269, and KRW 478 as of August 24, 201, and the Plaintiff was to have been paid out of KRW 208,000, KRW 160,000, KRW 810,000,00 for Defendant 20.