(영문) 수원지방법원 2015.11.12 2015가단45587

공사대금

Text

1. The Defendant’s KRW 132,00,000 as well as 5% per annum from September 1, 2015 to September 11, 2015 to the Plaintiff.

Reasons

1. The Plaintiff, on or around March 2015, entered into a construction subcontract with the Defendant to receive KRW 165,00,000 for electrical construction among the construction works for new factories C, Inc., Ltd., Inc., Ltd., in the Slified City B, and completed the construction, but did not receive the remainder of the construction cost, excluding KRW 33,00,000, out of the construction cost.

2. Judgment without any ground (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);

3. In accordance with the statutory interest rate under Article 3 (1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings for Partial Dismissal, the case that is concluded after October 1, 2015 is subject to the interest rate of 15% per annum from October 1, 2015 to the full payment, and thus, the part of the Plaintiff’s request shall be dismissed.