구상금
1. The defendant shall appoint the plaintiff (appointed party) and the appointed party:
A. Attached Form 1. The phrase "the principal of the claim No. 1" in the attached Table 1.
1. Basic facts
(a) A project operator who has completed the construction project of C Power Plants 7 and 8: The project operator who constructed the instant power plant and contributes to the stabilization of electricity supply and demand after 2008: the project period of 4,000 MW (500 MW level 8): January 1, 1982; from January 2008 to December 2, 2008: The project area: F- 7; 3,000 MW (50W level 6); 4,000 MM (50M), 1,000 MW (50W class 8), and 1,000 MM (50M class 20M), and the project period of 1,000 MM (50MM level 200M), approved by the Minister of Commerce, Industry and Energy, shall increase the area of electric power resource development project in the area of 287,500m21 to 258.251, 20582.
A) The Ministry of Commerce, Industry and Energy publicly announced the execution plan for electric power resource development business for the construction business (amended) as D/D (hereinafter “instant construction business”), and the said public announcement is called “instant public announcement”.
The main contents are as follows. 2) The power plant of this case was commenced on March 1, 2005 and completed around June 2009.
B. On August 18, 199, the plaintiffs (appointed parties; hereinafter referred to as the "Plaintiffs") and the designated parties (1) jointly share 4 hectares fishing ground located in the Griwon-gun, Chungcheongnam-gun, Chungcheongnam-do on August 18, 199 (hereinafter referred to as the "instant fishing ground").
(1) As to the term of validity of the license for fish farming, etc. (the license number H; hereinafter “instant fishery license”) until August 17, 2009, the term of validity of which expires; and the fishery right acquired therefrom is “the instant fishery right”.
2) On January 30, 2013, the Plaintiffs and the designated parties acquired the instant fishery right’s share ratio as indicated in the “share ratio” column in attached Table 1. The designated parties I lost all the instant fishery right’s share due to compulsory auction on January 30, 2013.
3) As to the instant fishery license, the former Fisheries Act (Act No. 1158, Dec. 18, 2012) shall apply.