도로점용허가신청불가통보처분취소
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. Details of the disposition;
A. On April 22, 2015, the Plaintiff filed an application for permission to occupy and use the primary road and the Defendant’s request for supplementation. On April 22, 2015, the Plaintiff is 3,105 square meters of B forest land (hereinafter “land reserved for gas filling stations”).
After completing the registration of ownership transfer with respect to the Plaintiff, on January 16, 2017, the Plaintiff filed a building report with the Defendant on the construction of gas charging stations on the said land. (2) In January 2017, the Plaintiff filed an application with the Defendant for permission to occupy and use a road of Taecheon-si, C road of 1,930 square meters, D forest land of 621 square meters, E roads (hereinafter “C roads, etc.”) and 10 square meters in total for each of the ten-meters of news reporting block by cutting off the news reporting block, and then paving them for ten years.
3) On January 19, 2017, the Defendant requested the head of Taecheon Police Station to present his/her opinion on the Plaintiff’s application for permission to occupy and use the road, and on January 19, 2017, “the relevant branch is deemed to have a high risk of accidents due to vehicle entry and exit at the time of opening an access road into and out of the two-lane sections.” Accordingly, on January 23, 2017, the Defendant demanded that the Plaintiff, on January 23, 2017, “the access road has a high risk of traffic accidents due to the four-lane road decline sections,” and that “the maintenance of a minimum separation distance pursuant to Article 6 of the Rules on Connection with Roads and other Facilities and meet the conditions for the installation of an alternative lane pursuant to Article 8 of the said Rules.”
B. The Plaintiff’s secondary application for permission to occupy and use the secondary road, etc. (1) around April 2017, is part of the part (797 square meters in total, 797 square meters in size and as soon as possible in the lower forest) of C road, etc. and F river 22,229 square meters in size.
A) A person has occupied and used the road for ten years and applied for the secondary permission to occupy and use the road for the installation of a two-dimensional change lane (hereinafter referred to as "forest 1"). (2) The defendant's side of the defendant is the Tae Yan Police Station, the Gangwon-do Branch of the Road Traffic Authority, and the Road Traffic Authority on April 4, 2017, as a result of on-site inspection, the point at issue is likely to cause accidents.