(영문) 서울동부지방법원 2015.06.05 2014가합101666

원상회복 등

Text

1. The Defendants are jointly and severally liable to the Plaintiffs for the amount of KRW 8,329,586,687 and the amount from April 11, 2014 to June 5, 2015.

Reasons

(b) The first unit of Seongdong-gu Seoul;

5. Total floor area: 461,679 square meters;

6. Floor area ratio: 315.98%;

7. A building plan;

(a) Scale: 3 to 25 main complexes with the 25th underground floors: 5 to 28 underground floors (hereinafter referred to as "three buildings");

8. Geological conditions: Standards for the general earth and sand.

9. Design conditions: The standard point of time for calculating the construction cost on August 16, 2007 (Tender Date): Article 3 (Construction Costs) (1) The average construction cost of building facilities (including apartments, business facilities, sales and cultural facilities, underground parking lots, and ancillary and welfare facilities) shall be KRW 3,49,000 per square year from the date of concluding the contract as the basic date, and the total construction cost shall be the amount calculated by multiplying the total floor area of final construction approved by the head of the competent Gu by the average construction cost.

(2) The construction cost of paragraph (1) shall be adjusted by applying the fluctuation rate of the lower between the consumer price index announced by the Ministry of Finance and Economy and the housing facility repair item index from the commencement of the construction cost to the commencement of the construction cost, and there shall be no increase or decrease in the construction cost due to price fluctuations after the commencement of the construction work, unless there is any reason attributable to the Defendant Union, for the increase or decrease in the construction cost due to price fluctuations.

The unit cost of construction under paragraph (1) shall be calculated according to the project conditions, such as the total floor area, floor area ratio, construction plan, geological conditions, and design conditions, which shall be adjusted when such conditions change.

Article 4 (Scope of Construction Works) (1) The scope of construction works included in the usual cost of construction works under Article 3(1) shall be as follows:

15. Basic relocation expenses: 16. Financial expenses for interest-free business expenses; 24. Directors' expenses: Article 6 (Adjustment of Construction Costs) (1) 3 million won per member household; in cases falling under any of the following subparagraphs, a mutual consultation shall be held within two months from the occurrence of the grounds: