추심금
1. The Defendant shall pay to the Plaintiff KRW 143,50,737 and the interest rate of KRW 15% per annum from April 11, 2018 to the date of full payment.
Description of Claim
Attached Form
same as the reasons for the claim.
However, the Plaintiff claimed damages for delay at the rate of 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the day following the day when a copy of the complaint was served to the Defendant, but the damages for delay under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings occurs from the day following the day when the copy of the complaint was served to the Defendant. Thus, the Plaintiff recognized damages for delay from April 11, 2018, the day following the day when the copy of the complaint was served
Articles 208(3)1 and 257(1) of the Civil Procedure Act of the applicable provisions of Acts (a judgment without a presentation of a written reply)