(영문) 서울중앙지방법원 2016.08.26 2016가단5148213

건물명도

Text

1. The defendant shall be the plaintiff.

(a) order each real estate listed in Schedule 1 and 2;

B. From June 28, 2016, Form 1 attached hereto.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Judgment without any applicable provisions of Acts (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);

3. Recognizing only damages for delay calculated at the rate of 15% per annum as stipulated in the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings, etc., as to damages for delay from the day following the delivery date of a copy of the complaint of this case concerning KRW 17,199,781 among the claims of this case