(영문) 대전고등법원 2015.10.22 2014나12018

소유권말소등기 등

Text

1. Of the judgment of the court of first instance, the part against the plaintiff ordering additional implementation is revoked.

Ga. The plaintiff Ga.

Reasons

1. The following facts may be found without any dispute between the Plaintiff and Defendant B, the Korea Labor Welfare Corporation, the National Pension Service, E, the J, the K, the Republic of Korea, the Siljin-si, the Han Bank, the Seongdong Saemaul Fund, and the N, or the overall purport of the entries and arguments in Gap evidence 1-1-5, Gap evidence 9-1-40, Eul evidence 9-1-5, Eul evidence 1-5, Eul evidence 1-5, and Eul evidence 1. The plaintiff and the other defendants shall be deemed to have led to confession in accordance with Article 150 of the Civil Procedure Act.

A. The Plaintiff among Q Q, who is six years of age of P in the OC City, is a family council comprised of 23 senior descendants in the RR area in Jinjin-si.

B. Defendant B was established on April 27, 2007 for the purpose of manufacturing and selling steel structure connecting parts by AC, T, etc.

T, the representative director of Defendant B, performed the Plaintiff’s overall duties from around 1994 to 1999, and C, the auditor and C, were the Plaintiff’s president from around 1999 to 2007.

C. On December 5, 2007, Defendant B completed the procedure for the transfer of ownership on the land of this case owned by the Plaintiff on December 3, 2007 (hereinafter “the first transfer registration”). On June 9, 2009, Defendant B completed the procedure for the transfer of ownership on the land of this case owned by the Plaintiff on May 3, 2009 (hereinafter “the second transfer registration”).

The remaining Defendants except Defendant B completed the provisional attachment registration, attachment registration, establishment registration of neighboring areas, establishment of superficies registration, etc. as indicated below with respect to each of the instant lands after the completion of each of the instant registrations of transfer Nos. 1 and 2.

The provisional attachment on September 3, 2009, - 3D on July 6, 2009, provisional attachment on July 14, 2009, attached on October 8, 201, by the National Pension Service on March 3, 2011, attached on November 17, 2009, on November 17, 2009, of the second land 3, 4,5 land 2 C 2 C on May 13, 2009 - 3D on provisional attachment on July 6, 2009, by the Korea Workers' Compensation and Welfare Service on July 7, 2010. - The National Pension Service on March 3, 2011, attached on November 17, 2009 - six sub-cuk Engineering on November 23, 2009.