beta
(영문) 대구지방법원 2018.10.19 2018가단112168

대여금

Text

1. As to KRW 60,00,000 and KRW 50,975,705 among the Plaintiff, the Defendant has 12% per annum from February 8, 2018 to March 9, 2018.

Reasons

1. The cause of the claim shall be as shown in the Appendix of the Director;

(However, among the description of the cause of the claim, the creditor and the debtor A shall be deemed the defendant.

2. However, since the defendant does not clearly dispute the plaintiff's assertion, it is deemed that the defendant led to confession of the cause of claim pursuant to Article 150 of the Civil Procedure Act.

Therefore, the Defendant is obligated to pay 60,00,000 won, the maximum amount of collateral guarantee and 50,975,705 won among loan obligations that Nonparty Company B owes to the Plaintiff, which are calculated by each of the annual rates of 12% per annum, from February 8, 2018 to March 9, 2018, the delivery date of a copy of the instant complaint (payment order) from February 8, 2018, and 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, which is the date of delivery of a copy of the instant complaint (payment order).

3. It is so decided as per Disposition by the assent of all participating Justices on the ground that the plaintiff's claim is justified.