(영문) 의정부지방법원 2018.10.11 2016구합7274

손실보상금

Text

1. The Defendant’s KRW 91,549,852 as well as the Plaintiff’s KRW 5% per annum from February 12, 2016 to October 11, 2018.

Reasons

- Business recognition and public announcement - Road Business - Private Investment Project - Public Announcement - on June 5, 2012 - Defendant - Project operator - Compensation for consultation on March 3, 2014: Loss arising from the business suspension of 164-2 located in Mancheon-si, Mancheon-si (hereinafter “instant business”): 030, 200, 300, 306, 306, 208, 30, 306, 70, 306, 30, 306, 70, 300, 430, 431, 408, 400, 431, 400, 506, 506, 160, 506, 160, 706, 705, 706, 706, 706, 706, 706, 506, 106,

The Central Land Tribunal’s ruling of expropriation on December 17, 2015 (hereinafter “instant ruling”): Loss from the suspension of business of the instant case - An appraisal corporation, the Korea Appraisal Corporation, and the Korea Appraisal Board (hereinafter “Appraisal Board”) (hereinafter “instant appraisal”) - The date of the commencement of expropriation: February 11, 2016 - Compensation for business suspension: 151,28,660 won (the instant appraisal panel was assessed as compensation for business suspension on the premise that the period of suspension under the transfer of the instant business is three months, and the average of the appraised amount is lower than the average appraised amount of the instant appraisal, and compensation for business suspension was determined based on the average appraised amount of the instant consultations). The result of the appraisal by the court below is below.