beta
(영문) 서울북부지방법원 2015.11.05 2015가단124566

양수금

Text

1. The Defendants are jointly and severally liable to the Plaintiff for KRW 103,058,59 and KRW 80,000,000 among them.

Reasons

1. Claims against the defendant A and B

(a) Indication of claims: To be as shown in the reasons for the claims;

(b) Grounds: Judgment by public notice (Article 208 (3) 3 of the Civil Procedure Act);

2. According to the evidence No. 1 to No. 14 of the claim No. 1 against the defendant C, the defendant C has the obligation to pay the plaintiff the loan principal amount of KRW 100 million with interest rate of KRW 19% per annum on October 12, 2007 under the joint and several guarantee of the defendant C, the loan credit amount of KRW 100 million was transferred before transfer, and the defendant took over the loan credit amount of KRW 4, 2014, and the above transfer was notified to the defendant C around that time. On January 21, 2015, the fact that the loan principal amount of KRW 80 million was KRW 23,058,599, and the interest rate of KRW 80 million with interest rate of KRW 103,058,59 and the interest rate of KRW 19% per annum from January 22, 2015 to the day of full payment.

Therefore, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.