(영문) 광주지방법원 목포지원 2016.11.24 2016고정282

업무방해

Text

Defendants shall be punished by a fine of one million won.

In the event that the Defendants did not pay the above fines, only 100,000.

Reasons

Punishment of the crime

Defendant

A is the Director of the Complex Management Agency, Defendant B is the representative director of the same company, and Defendant C is the same company management director.

The Defendants, “2016 High 282” (the Defendants), while performing the construction work for the construction of the Fanmar-gun F rural village connections, contracted from Hamyeong-gun, would be avoided by obstructing the progress of the construction work, under the assertion that the Defendants, for the purpose of claiming for additional progress payment, exercised a lien to preserve the state of the construction site, in addition to the construction cost already received from Hamyeong-gun, for the purpose of claiming for additional progress payment, in addition to the construction cost already received from Hamyeong-gun.

1. Defendant A

A. At around 13:00 on June 10, 2015, the Defendant obstructed the victims’ legitimate construction work by force by parking a large of 4 hours per hour until 16:00 on the work route of Pokes, and obstructing the victims’ legitimate construction work by force, in order to ensure that the parts belonging to the State, such as the victim G, etc., are engaged in the field of construction of a rural village connected road, and the parts belonging to the State, such as the victim G, etc., are unable to proceed with the excavation work.

B. At around 08:00 on June 16, 2015, the Defendant prevented the victims from proceeding creammen on a H rocketing vehicle in order for the victims’ and other employees belonging to the State, including G, etc., to conduct twitter operations, and obstructed the victims’ legitimate work by force by way of force on the part of the victims’ work course.

2. Defendant B, at the same time and place as set forth in paragraph (a) of Article 1, intends to move Hyren vehicle at around 16:00 on June 10, 2015, Defendant B, from that time, to June 11, 2015, to prevent the progress of approximately 20 hours of cargo vehicles of approximately 1 ton owned by the Dispute Settlement Bank Co., Ltd., from being parked in front of the said paragraph and by force, G, etc., the victim, by means of force.