beta
(영문) 창원지방법원마산지원 2015.09.02 2014가단16404

공사대금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

The Plaintiff asserted that, on October 2013, 2013, the Defendant completed the above construction work after being awarded a contract with the Defendant for the construction cost of KRW 1.8 million at the window C of Changwon-si, the Defendant is obligated to pay the said construction cost and delay damages to the Plaintiff. However, the witness E’s testimony is difficult to believe, and other evidence submitted by the Plaintiff alone is insufficient to recognize that the Plaintiff was contracted with the above construction work from the Defendant, and the Plaintiff’s assertion is without merit.

Thus, the plaintiff's claim is dismissed as there is no ground.