(영문) 대전지방법원홍성지원 2017.09.26 2016가단11233

보증금반환

Text

1. The Defendant’s KRW 20 million to the Plaintiff and the Plaintiff’s KRW 6% per annum from December 1, 2016 to September 26, 2017.

Reasons

1. Basic facts

A. On November 17, 2014, the Plaintiff entered into a contract between the Plaintiff and Sejong Special Self-Governing City Water and Wastewater Works Office (hereinafter “SP”) and the Sejong Special Self-Governing City Water and Wastewater Works Office (hereinafter “SP”) for the part of the Civil Works Works in the Development of Water and Wastewater in Geumnam-do” (hereinafter “instant Construction Works”).

(2) As to the contract amount of KRW 2,089,072,120, 90, 909,494,90, 818, 313,360, and 818, 2015, 313,360, and 818, and 27, 2015, 3% of the total completion date of the contract, 3% of the deposit amount, 62,672, and 164, as to the contract amount (hereinafter “instant contract”). Of the instant contract, the part of the said contract amount of KRW 909,494,90, and September 24, 2015, 2015, is “1 minute contract.”

(2) On February 27, 2015, the Plaintiff entered into a contract with the Sejong Water and Wastewater Construction Business Office on the second part of the instant construction works with the terms “2,089,072,120 won”, “984,739,00 won for the contract amount,” “313,360,818 won for the contract deposit,” “315,23, 2015,” “316, 27, 2016,” “3% of the total completion date,” “3% of the deposit fee,” “62,672,164 won for the deposit,” and “23, 2015,” with respect to the second part of the instant construction works (hereinafter “contract contract amount”). < Amended by Act No. 984, Jul. 27, 2016>

3) On September 16, 2015, the Plaintiff and the Sejong Water and Wastewater Works Office entered into the instant contract on the grounds that the contract amount of the first minute contract was modified, etc., with “2,213,598,540 won for the first minute contract amount,” “2,213,598,540 won for the second minute contract amount,” “32,039,781 won for the contract deposit,” “32,039,781 won for the contract deposit,” “3% for the completion date,” “36,407,956 won for the defect deposit,” “3% for the defect deposit,” and “6,407,956 won for the second minute contract amount,” and “1,094,429,000 won for the second minute contract amount,” and “total construction work,” around March 2016.