beta
(영문) 수원지방법원 2020.01.09 2019가합28952

대여금

Text

1. The Defendant shall pay to the Plaintiff KRW 250 million and the interest rate of KRW 20 million per annum from January 9, 2018 to the day of complete payment.

Reasons

The fact that the Defendant borrowed KRW 250 million from the Plaintiff on January 8, 2018 is determined as the due date of repayment on December 21, 2018 and as the interest rate of KRW 20 million, respectively, is no dispute between the parties.

The defendant is obligated to pay to the plaintiff interest or delay damages calculated at the rate of 20% per annum from January 9, 2018 (the day after the day after the day of the above loan) to the day of full payment.

The plaintiff's claim is reasonable, and it is so decided as per Disposition.