(영문) 전주지방법원 2015.01.28 2012가합4243

공사대금

Text

1. The Defendant’s KRW 193,218,291 as well as 5% per annum from July 28, 2012 to January 28, 2015 to the Plaintiff.

Reasons

1. Facts of recognition;

A. From August 24, 201, the Plaintiff was running the construction of a new building (hereinafter “instant construction”) of a detached house (a store and multi-family house) (hereinafter “the instant building”) on the site in the front city located in the Seoul Special Metropolitan City owned by the wife (hereinafter “instant construction”) from around August 24, 201, and the Defendant and the Plaintiff completed the instant construction on October 20, 201, and the Plaintiff completed the construction on December 30, 201; the time limit for completion; the construction price of KRW 417 million (including value-added tax); the contract deposit of KRW 35 million (the payment date: October 20, 201); the intermediate payment of KRW 160 million (the payment date: November 10, 201); the remainder of the construction payment of KRW 220 million (the remainder of the construction payment date); the remainder of the construction payment of KRW 130 million (the remainder of the construction payment date: 10 million) and the remainder of the construction payment amount of KRW 13 million (the remainder of the remainder.

2. The name of the owner shall be changed on the date of intermediate payment;

3. A contract in the present state shall be based on mutual screen pictures; and

On October 21, 2011, the Defendant (contractor) shall succeed to the right to collateral security of land on the remainder date of land (the intermediate date of construction supply and demand contract) and the financial costs of land loans shall be borne by the Defendant (contractor).

In addition to special terms and conditions, “the construction and installation of four stories for the fourth floor and the rooftop, i.e. the main building, are equivalent to all the attached parts, such as the tap water, etc.), which is currently being constructed on October 201, 201, - the construction agreement on the construction details (hereinafter “instant construction agreement”) with the main contents of construction works, including additional costs, and the roof roof materials for the entire building, installed after discussion - singing (additional costs).

B. On October 18, 201, the Plaintiff received each payment from the Defendant, respectively, of KRW 35 million as the contract deposit, KRW 1330 million as the intermediate payment on November 10, 201, and KRW 40 million as of December 28, 201.